The Healthcare sector has very demanding requirements for contractors like us to be aware of, which means that you cannot just use any building contractor to perform the works. Working with us guarantees you that you can rely on us to have the required Experience and Knowledge to fulfil your requirements in order to build a safe and healthy environment for your staff to work in and your patients to be treated in.
We understand the importance of using products that are compliant with the latest health codes such as HBN 00-10 (part A to D), which includes guidance on flooring, walls and ceilings, sanitary assemblies and windows in healthcare facilities. This was formerly the HTM64 guidance system. We also work in line with Outcome 8 of the CQC’s ‘Essential Standards of Quality and Safety’ to control infection and promote cleanliness and hygiene.
We realise the importance of good communication, especially when we work in live environments and occupied spaces, so that we can provide a safe, practical and cost effective solution to your needs with minimal interruptions to your daily operational activity. This approach has been well received by all clients, especially in Healthcare and has been reflected in our testimonials.
Kingston Hospital
The new CT scanner project was completed in 2022
The enabling works for the installation of the new CT scanner project took 6 weeks to complete.
The objective of this project was to supply, install, test and commission the CT3 scanner within the outpatient’s department at Kingston Hospital.
-
Install a LV switchboard and cables
-
Strip out heater and associated pipework
-
Function, testing and commissioning of installed items
-
Builders works in connection & fire stopping
-
Training of client representatives into the safe and correct method of operation
Chelsea and Westminster – IR Scanner
Pre – installation refurbishment works to the existing IR room to prepare for the new IR equipment.
Read MoreUnique arts studio at Chelsea & Westminster
The new CW +Studio – is a bespoke multi-functional art and cultural space at Chelsea and Westminster Hospital.
The Studio welcomes patients as part of an award-winning performance and participatory programme Arts for All.
Read MoreNell Gwynne ward at Chelsea & Westminster Hospital
The project comprises the refurbishment of the Nell Gwyne ward. Works completed in 10 weeks another major effort by all involved. Works including:
Read MoreKingston Hospital – Endoscopy Ward Refurbishment
Kingston Hospital – Endoscopy ward refurbishment
Completed September 2020 of the refurbishment of the endoscopy ward. The project included installation of the steel deck to accommodate the 2 AHU, chiller and BMS panel on roof level to service the new endoscopy ward on Level 7.
Read More
Kingston Hospital NHS
Kingston Hospital NHS – Kingston Coombe Ward project.
Reception area refurbishment including demolition of walls, strip-out (floor/ceilings) new doors + screens.
Read MoreOffice conversion to provide new maternity unit
Conversion of existing office space to provide new ward bed bays and clinical examination rooms.
Read MorePatient transport lounge
Reconfiguration of various office and corridor areas to provide new reception for the X-ray department. Workings included all new M&E services flooring, wall cladding doors nurse call system and reception desk.
Read MoreSt Georges Hospital – Trevor Howell Ward
The refurbishment and alteration of the existing chemo chair unit.
Read MoreJupiter & Neptune Paediatric Ward refurbishment
Critical services including new medical gases, nurse call system, UPS, and telemetry updates with programmed services interruptions.
Read More